VERONA
METALLURGICAL PLANT
Spin the wheel down or click the sign
FACILITY DETAILS:
One of the largest projects on modernization of lighting system at industrial enterprises of the European market.
Location:
Italy, Verona
Scope of business activities:
Production of rolled steel
OBJECTIVES:

1.Uniform lighting of premises.

2.Compliance with lighting standards.

3.Energy saving.

4.Release of electric power for use in production process

Spin the wheel down or click the sign
SITUATION BEFORE MODERNIZATION:

The lighting parameters do not conform to the standards.

ENERCOM solution was selected as the most cost-effective based on the total cost of ownership (TCO) of the lighting system.

RESULT:

After the facility commissioning we managed to achieve the following indicators:

  1. Power consumption reduced by 70%
  2. Lighting level increased by 70%
  3. Savings per 1,000 sq.m a year: EUR 6,000
  4. Project payback period – 3 years
  5. Increased comfort of work and reduced risk of injury
  6. Lighting area, sq.m – 33,000