On December 27, a video about the modernization of the lighting system at the Seversky Pipe Plant (STZ), carried out by ENERCOM, was released on the Polevskoy regional TV channel.
At present, ENERCOM is implementing a project for STZ to upgrade the industrial lighting system according the following customer’s goals:
- reduction of the energy consumption of the lighting system by more than 80%;
- introduction of modern illumination standards to increase workforce productivity and product quality;
- improving the security level and setting up separate accounting of consumed energy.According to the results of the first stages of work and control measurements, all planned performance indicators were met:
- the energy consumption level was reduced by 80%;
- the level of illumination has been increased by 3 times and brought in line with modern standards of 200 Lx.Installation of light fixtures was carried out under difficult conditions:
production processes did not stop, there were oil vapors and dust in the air.
Because the temperature in the workshops can rise as high as +50°C, the light fixtures were additionally treated with an oleophobic coating, which prevents particles from sticking and simplifies maintenance of lighting equipment.The unique design features of ENERCOM light fixtures made it possible to reduce the number of mounting points.
All lighting devices are of uniform construction that makes their maintenance easier.The ENERCOM specialists have also installed lighting metering devices for separate accounting of energy resources and their competent management.
New wiring and lighting switchboards have been added to ensure fire safety and stable operation of the lighting system.